Technical Study of the Implementation Method for Lightweight Brick Wall Construction: Analysis of Cost, Time, and Quality in Building Construction Projects

Authors

  • Mutia Ramadhany Department of Civil Engineering, Faculty of engineering and computer science, Jakarta Global University, 16412, Indonesia
  • Aulia Choiri Windari Department of Civil Engineering, Faculty of engineering and computer science, Jakarta Global University, 16412, Indonesia

DOI:

https://doi.org/10.56904/j-gers.v5i1.154

Keywords:

Lightweight Masonry Wall, Cost, Building Construction, time, Quality

Abstract

The construction of lightweight masonry walls plays a crucial role in supporting building stability, aesthetics, and comfort. This study aims to analyze the implementation methods of lightweight masonry walls in terms of cost, time, and quality in the Sky House Alam Sutera project. The research uses a descriptive-analytical approach with case study and literature review, involving field observation, interviews, technical documentation, and analysis of the project Budget Plan (BoQ) and technical standards. The results indicate that the material requirements per floor include 84,000 lightweight bricks, 60 sacks of cement, and 36 m³ of sand, with an estimated total cost of approximately IDR 260 million, including labor and overhead. The deployment of five parallel work teams allows wall installation per floor to be completed in about 28 days, including finishing, quality inspection, and curing. The use of thin bed mortar increases installation efficiency while maintaining proper thickness and alignment. Consistent quality control through visual inspection, compressive testing, and daily documentation ensures compliance with technical standards. The study emphasizes careful planning, labor coordination, and strict quality supervision to achieve efficiency in cost, time, and quality in multi-story building projects.

References

[1] K. Srimuang, T. Imjai, F. Kefyalew, S. N. Raman, R. Garcia, and S. Chaudhary, “Thermal and acoustic performance of masonry walls with phase change materials: A comparison of scaled-down houses in tropical climates,” Journal of Building Engineering, vol. 82, p. 108315, Apr. 2024, doi: 10.1016/j.jobe.2023.108315.

[2] A. Bilgil, O. Şimşek, Ö. Sevim, and İ. Demir, “Development of lightweight and thermally efficient clay bricks using expansion additives: Effects of firing temperature and additive ratios on physicomechanical properties,” Journal of the Australian Ceramic Society, vol. 61, pp. 1351–1363, 2025, doi: 10.1007/s41779-025-01170-7.

[3] Z. Mustapha, B. B. Akomah, and S. K. Ansah, “Construction projects success: Time, cost, quality and safety,” International Journal of Research and Innovation in Social Science (IJRISS), vol. 7, no. 9, pp. 680–688, Sep. 2023, doi: 10.47772/IJRISS.2023.70958.

[4] J. Zhou, Y. Tang, and Y. Tian, “Multi-objective trade-offs for construction projects with dual constraints of schedule risk and resources under a risk-driven perspective,” Sustainability, vol. 17, pp. 1–34, 2025, doi: 10.3390/su17051926.

[5] A. Thakur and S. Kumar, “Evaluation of cost effectiveness of using autoclave aerated concrete (ACC) blocks in building construction,” Materials Today: Proceedings, vol. 51, pt. 1, pp. 1063–1068, 2022, doi: 10.1016/j.matpr.2021.07.095.

[6] L. Jia, T. Qiu, R. Yu, W. Lu, and Z. Liu, “BIM-enabled two-phase optimization framework for automated masonry layout efficiency,” Buildings, vol. 15, pp. 1–23, 2025, doi: 10.3390/buildings15173051.

[7] P. Praveen and D. Jaysawal, “Comparative study of clay bricks and AAC blocks,” International Journal of Structural Design and Engineering, vol. 5, no. 1, pp. 10–14, 2024.

[8] S. A. Mohammed and A. Hasan, “Analyzing cost deviation factors in Iraqi construction projects: A comprehensive examination of influencing variables,” Engineering, Technology & Applied Science Research, vol. 14, no. 3, pp. 13897–13901, 2024, doi: 10.48084/etasr.6999.

[9] O. M. ElSahly, S. Ahmed, and A. Abdelfatah, “Systematic review of the time-cost optimization models in construction management,” Sustainability, vol. 15, pp. 1–20, 2023, doi: 10.3390/su15065578.

[10] H. Medriosa and F. A. Akbar, “Analisis struktur gedung IRNA (Instalasi Rawat Inap) Rumah Sakit Umum Pasaman Barat menggunakan SNI Beton Bertulang 2847:2019 dan SNI Gempa 1726:2019,” Ensiklopedia of Journal, vol. 3, no. 4, pp. 7–14, Jul. 2021, doi: 10.33559/eoj.v3i4.796.

[11] J. I. Deza, H. Ihshaish, and L. Mahdjoub, “A machine learning approach to classifying construction cost documents into the International Construction Measurement Standard,” arXiv preprint arXiv:2211.07705, pp. 2–12, 2022, doi: 10.48550/arXiv.2211.07705.

[12] A. Ibrahim, T. Zayed, and Z. Lafhaj, “Enhancing construction performance: A critical review of performance measurement practices at the project level,” Buildings, vol. 14, pp. 1–42, 2024, doi: 10.3390/buildings14071988.

[13] M. Ghazal and A. Hammad, “An integrated planning and control framework (IPCF) for construction projects—Step 1: Development of the construction data hub (CDH),” Buildings, vol. 13, pp. 1–24, 2023.

[14] A. Abasi, B. Banting, and A. Sadhu, “Experimental evaluation of compressive properties of early-age mortar and concrete hollow-block masonry prisms within construction stages,” Materials, vol. 17, pp. 1–20, 2024, doi: 10.3390/ma17163970.

Downloads

Published

2026-06-30

How to Cite

Mutia Ramadhany, & Choiri Windari, A. (2026). Technical Study of the Implementation Method for Lightweight Brick Wall Construction: Analysis of Cost, Time, and Quality in Building Construction Projects. Journal of Global Engineering Research and Science, 5(1), 30–36. https://doi.org/10.56904/j-gers.v5i1.154
Views
  • Abstract 11
  • PDF (English) 7